Progress Update: 11.12.2025

Construction continues to advance both inside and out. Asphalt paving and parking lot striping are complete, and the bio-retention basin has been installed. Landscaping activities are now underway, adding the finishing touches to the site.

Permanent power has been activated, allowing interior work to progress efficiently. Casework installation is in progress, ceiling tiles and light fixtures are being placed, and exterior canopies are moving forward. Fencing installation is nearly complete, marking another step toward project completion.

Wright Construction is proud to deliver this critical public safety facility, designed to strengthen law enforcement resources and community safety across St. Louis County.

Broke Ground: 06.05.2024

Predicted Completion: Summer 2026