Project Update: First Community Credit Union – Tesson Ferry Branch

First Floor
Wall closures are nearing completion, with wall finishing actively in progress. Interior finishes on this level are scheduled to begin in the coming weeks.

Second Floor
Interior finishes are progressing quickly. The first coat of paint is complete, and ceiling and flooring installations are currently underway.

Exterior Work
Starting in August, crews will begin the next phase of exterior construction. This will include removing and replacing most of the front parking lot and installing a brand-new front entrance canopy to welcome members into the updated space.

Stay tuned for more updates as construction continues to move forward!