ST. CLAIR ANIMAL SERVICES FACILITY
UPDATE: May 20, 2025
- Concrete foundations are complete.
- Underground plumbing in the dog kennels is underway.
- Masonry is ~ 50% completed
- Electric work ongoing
Looking forward:
- Underfloor Radiant heat
- Concrete slab on grade
- Structural steel erection